GENERAL POINTS ON TRENCH EXCAVATION
Installation of HDPE systems requires a minimal trench width,
therefore considerable saving can be made in terms both of reduced labour costs
and less soil to be moved.
Additionally, reinstatement costs are cut and where needed smaller
quantities of imported backfill are required.
The dimensions of a trench
line opening are normally governed by the pipe diameter, method of jointing and
site conditions. Normal minimum
depth of cover for mains should be 900mm from ground level to the crown of
the pipe. Trench width
should be as narrow as possible, but never less than the
outside diameter of the pipe
plus 250mm to allow for correct compaction of side
fill.
In some instances it may be
acceptable to lay HDPE pipe directly
on the bottom of the trench - but only where the soil is uniform,
relatively soft and fine-grained without large flints, stones and other hard
objects. The trench
bottom should be brought to an even finish,
providing consistent support for pipes along their whole length.
In other cases,
the trench should be cut to a depth
which will allow for the necessary thickness of selected bedding
material below the bottom of the pipe. If soil from the
excavation is unsuitable, granular material should be
imported. Gravel or
broken stone