
|
LAYING Of PIPE
While designing the pipeline systems, the level and depth of the trench is calculated depending on factors such as terrain and the usage to which the pipeline is to be put. Excavation and pipe laying must take place simultaneously as leaving open trenches for too long makes them unsuitable for use. As pipe laying advances, trenches must be blackfilled immediately.
The pipe jonts, however, should be left exposed until later the pipeline system has been tested. The minimum width of the trench must be equal to the pipe diameter plus 300-mm. At the crown of the pipe, the trench width must not exceed the pipe diameter plus an additional 600-mm. There are two types of trench formation: |
|
Direct Laying:
The fornation of the trench must consist of stable, uniform and smooth soil devoid of irregularities for direct laying of pipes. The bed of the trench should be smoothed out evenly to provide uniform support to the pipe laid. There will be some extra excavations to enable adequate jont assembly and pipe support.
Pipe laying on Bedding:
Pipe laying, where soils are unsuitable for direct pipe laying , trenches must be excavated to an additional depth of 100mm at the minimum and suitable bedding, as detailed later, must be utilized for pipe laying, under serve conditions it may become necessary the depth of the bedding even further. |
Bedding Material:
It should be stable and have a granular texture, free from impurities such as stones or other debris. Bedding which might change its properties under conditions such as stones or other debris. Bedding which might change its properties under conditions such as water seepage or freezing must be avoided. Preference must be given to free draining sand or nominal single size gravel with rounded or angular partical size 100mm or even 5mm to 10mm graded. After placing the bedding material in the trench it should be compacted by hand to provide the most even support. Special care needs to be taken for sockets holes and proper compaction in this area must be ensured. When backfilling a trench make sure that there are no foreign material left inside.
Backfill:
Pipe laying and back filling must take place simultaneously and installed pipeline systems must not remain exposed for longer periods than is absolutely necessary. The backfill must be devoid of irregularities like debris and stones and should be compacted by hand. Mechanical compaction should take place only when a buffer of 30cms has been built between the uPVC pipes and the surface being compacted. At least 76cms of cover should be allowed over the pipeline system in case vehicular traffic is expected to cross over the pipeline location at a later stage. Wherever extra protection to the pipeline is required, it is a good idea to provide concrete slabs on a cushion of granular fill. Extra protection may also be made possible by passing the pipe through an extra pipe duct of greater diameter. This is necessary only if the cover depth is less than 60cms. For cover depths of more than 60cms, well-compacted granular fill serves the purpose adequately. Under no circumstances is a concrete encasement of the pipeline desirable since it lessons the flexural strength of the pipeline system.
|
|
|